Construction Materials

6 Questions
GATE→2025→Construction Materials and Management→Construction Materials
Q1
MCQ[1 Mark]
Identify the FALSE statement from the following options regarding concrete compressive strength:
GATE→2025→Construction Materials and Management→Construction Materials
Q2
NAT[1 Mark]
If weights retained on 2.36 mm, 1.18 mm, 600 μm600\,\mu\text{m}, and 300 μm300\,\mu\text{m} sieves are 30%, 35%, 15%, and 20%, the fineness modulus is
GATE→2024→Construction Materials and Management→Construction Materials
Q3
MCQ[1 Mark]
Concrete of characteristic strength 30 MPa is required. If 40 specimens are tested, the minimum number having at least 30 MPa strength should be
GATE→2023→Construction Materials and Management→Construction Materials
Q4
MCQ[1 Mark]
Creep of concrete under compression is defined as the
GATE→2023→Construction Materials and Management→Construction Materials
Q5
MCQ[1 Mark]
In cement concrete mix design, with the increase in water-cement ratio, which one of the following statements is TRUE?
GATE→2022→Construction Materials and Management→Construction Materials
Q6
MCQ[1 Mark]
Which of the following equations is correct for the Pozzolanic reaction?

Construction Management

5 Questions
GATE→2025→Construction Materials and Management→Construction Management
Q7
MSQ[2 Marks]
In the context of construction project management, which of the following statements is/are true:
GATE→2024→Construction Materials and Management→Construction Management
Q8
MCQ[1 Mark]
Consider statements P (Preliminary estimate used for budgeting) and Q (Detailed estimate used for controlling costs). Which option is CORRECT?
GATE→2024→Construction Materials and Management→Construction Management
Q9
MCQ[1 Mark]
The figure shows formwork shores S1 to S5 for casting a cantilever RC beam. The correct sequence of removing shores is
Figure for Question 9
GATE→2024→Construction Materials and Management→Construction Management
Q10
NAT[2 Marks]
Initial cost Rs. 1,00,000, salvage value Rs. 10,000, life 5 years. Difference in depreciation (in Rs.) computed using double-declining balance and straight-line method in Year-2 is
GATE→2022→Construction Materials and Management→Construction Management
Q11
MCQ[2 Marks]
Project activities table given. Which option correctly states total duration and critical path?